Details of 'DEN/ESI-0019142-2' Work Item Schedule
Code Status Milestone Action Action Nb Target Achieved Version
0 Creation of WI by WG/TB Creation of WI by WG/TB     2012-06-07 2012-06-07
0 a TB adoption of WI TB adoption of WI     2012-06-06 2012-06-07
1 Start of work Start of work     2012-06-07 2013-04-02
2 Early draft Early draft     2013-07-30 2013-09-09 0.0.1
4 Stable draft Stable draft     2013-11-30 2013-11-11 0.0.2
4 Stable draft Stable draft     2013-11-11 2013-11-28 0.0.3
4 Stable draft Stable draft     2014-11-30 2014-09-15 0.0.4
2 Early draft Early draft     2014-09-15 2014-12-02 0.0.5
4 Stable draft Stable draft     2015-01-06 2015-01-12 0.0.6
4 Stable draft Stable draft     2015-01-12 2015-02-13 0.0.8
6 Final draft for approval Final draft for approval     2015-04-30 2015-04-30 0.0.9
6 Final draft for approval Final draft for approval       2015-06-08 0.0.10
7 A Start of TB approval process Start of TB approval process     2015-04-30  
7 B End of TB approval process End of TB approval process     2015-05-28  
8 TB approval TB approval     2015-06-04 2015-06-08 0.0.10
8 A Draft receipt by ETSI Secretariat Draft receipt by ETSI Secretariat     2015-06-22 2015-06-08
9 B Start of EN Approval Procedure Start of EN Approval Procedure
Access the e-approval application
AP 20151028 2015-06-30 2015-06-30 1.0.0
9 C End of EN Approval Procedure End of EN Approval Procedure     2015-10-28 2015-10-28
9 D Start of TB review after AP comments Start of TB review after AP comments     2015-10-28 2015-10-28
9 Dr Draft Review after PE Draft Review after PE     2015-11-30 2015-11-30 1.0.1
9 Dr Draft Review after PE Draft Review after PE     2015-12-07 2015-12-07 1.0.2
9 Dr Draft Review after PE Draft Review after PE     2015-12-11 2015-12-11 1.0.3
9 Dr Draft Review after PE Draft Review after PE     2015-12-17 2015-12-17 1.0.4
9 DaA Start of TB approval process Start of TB approval process     2015-12-17  
9 DaB End of TB approval process End of TB approval process     2016-01-14  
9 Da TB approval after review of AP comments TB approval after review of AP comments     2016-01-15 2015-12-17 1.0.4
9 E Draft receipt by ETSI Secretariat Draft receipt by ETSI Secretariat     2015-12-24 2015-12-17
10 F Start of Vote Start of Vote
Access the e-approval application
V 20160401 2016-02-01 2016-02-01 1.1.0
10 G End of Vote End of Vote     2016-04-01 2016-04-01
11 Vote result determination (adopted) Vote result determination (adopted)     2016-04-01 2016-04-01
12 Publication Publication PU   2016-04-15 2016-04-12 1.1.1