2020-08-12 Version 2.3.3
Simple Search | Advanced Search | Pre-Defined Reports | Help

Details of 'REN/CYBER-0048' Work Item Schedule
Code Status Milestone Action Action Nb Target Achieved Version
0 Creation of WI by WG/TB Creation of WI by WG/TB     2019-04-30 2019-04-30
0 p WI proposed to TB WI proposed to TB       2019-05-16
0 a TB adoption of WI TB adoption of WI     2019-05-17 2019-06-12
1 Start of work Start of work     2019-05-17 2019-07-09
2 Early draft Early draft        
4 Stable draft Stable draft       2019-07-09 0.0.1
4 Stable draft Stable draft       2019-08-06 0.0.2
4 Stable draft Stable draft       2019-08-20 0.0.3
4 Stable draft Stable draft       2019-09-03 0.0.4
4 Stable draft Stable draft       2019-09-09 0.0.5
4 Stable draft Stable draft       2019-09-17 0.1.0
6 Final draft for approval Final draft for approval       2019-10-12 0.1.1
6 AA Start of pre-processing Start of pre-processing     2019-10-28 2019-10-15
6 Final draft for approval Final draft for approval       2019-10-28 0.1.2
6 Final draft for approval Final draft for approval       2019-10-30 0.1.3
6 AB End of pre-processing End of pre-processing     2019-11-04 2019-11-12
6 Final draft for approval Final draft for approval       2019-11-12 0.1.4
6 Final draft for approval Final draft for approval       2019-11-14 0.1.5
6 Final draft for approval Final draft for approval       2019-11-15 0.2.0
8 TB approval TB approval     2019-10-30 2019-11-15 0.2.0
8 A Draft receipt by ETSI Secretariat Draft receipt by ETSI Secretariat     2019-11-29 2019-11-18
9 B Start of EN Approval Procedure Start of EN Approval Procedure
Access the e-approval application
AP 20200224 2019-11-26 2019-11-26 2.0.0
9 C End of EN Approval Procedure End of EN Approval Procedure     2020-02-24 2020-02-24
9 CA Start of comments categ. Assessment Start of comments categ. Assessment       2020-02-25
9 CB End of comments categ. Assessment End of comments categ. Assessment       2020-02-27
9 D Start of TB review after AP comments Start of TB review after AP comments     2020-02-24 2020-02-27
9 Dr Draft Review after PE Draft Review after PE     2020-03-27 2020-03-27 0.2.1
9 Dr Draft Review after PE Draft Review after PE     2020-03-29 2020-03-29 2.0.2
9 Dr Draft Review after PE Draft Review after PE     2020-03-30 2020-03-30 2.0.3
9 Dr Draft Review after PE Draft Review after PE     2020-03-30 2020-03-30 2.0.4
9 Dr Draft Review after PE Draft Review after PE     2020-04-01 2020-04-01 2.0.5
9 Dr Draft Review after PE Draft Review after PE     2020-04-06 2020-04-06 2.0.6
9 Dr Draft Review after PE Draft Review after PE     2020-04-06 2020-04-06 2.0.7
9 Dr Draft Review after PE Draft Review after PE     2020-04-07 2020-04-07 2.0.8
9 DaA Start of TB approval process Start of TB approval process     2020-04-07  
9 DaB End of TB approval process End of TB approval process     2020-05-05  
9 Da TB approval after review of AP comments TB approval after review of AP comments     2020-05-11 2020-04-09 2.0.8
9 E Draft receipt by ETSI Secretariat Draft receipt by ETSI Secretariat     2020-04-16 2020-04-09
10 F Start of Vote Start of Vote
Access the e-approval application
V 20200619 2020-04-20 2020-04-20 2.1.0
10 G End of Vote End of Vote     2020-06-19 2020-06-19
11 Vote result determination (adopted) Vote result determination (adopted)     2020-06-19 2020-06-19
12 Publication Publication PU   2020-07-03 2020-06-29 2.1.1

ETSI Home Page Any comments or problems with this application? Please let us know...