Code Status Milestone Action Action Nb Target Achieved Version
0 Creation of WI by WG/TB Creation of WI by WG/TB     2015-03-24 2015-03-24
0 gp WI proposed to WG WI proposed to WG       2015-03-24
0 p WI proposed to TB WI proposed to TB       2015-03-26
0 p WI proposed to TB WI proposed to TB       2015-03-26
0 a TB adoption of WI TB adoption of WI     2015-03-25 2015-03-26
0 E EC informed of mandated WI EC informed of mandated WI     2018-10-01 2018-09-21
0 Er EC mandate confirmed EC mandate confirmed     2018-10-26 2018-11-07
1 Start of work Start of work     2015-03-26 2015-05-11
2 Early draft Early draft     2015-04-17 2015-05-11 0.0.1
2 Early draft Early draft       2015-07-29 0.0.2
6 Final draft for approval Final draft for approval       2016-01-13 0.0.3
6 Final draft for approval Final draft for approval       2016-01-13 0.0.4
6 Final draft for approval Final draft for approval       2016-01-15 0.0.5
6 Final draft for approval Final draft for approval       2016-02-01 0.0.6
7 WG approval WG approval     2016-01-26 2016-02-01
8 TB approval TB approval     2016-02-26 2016-02-23 0.0.6
8 A Draft receipt by ETSI Secretariat Draft receipt by ETSI Secretariat     2016-03-08 2016-04-14
9 B Start of EN Approval Procedure Start of EN Approval Procedure
Access the e-approval application
AP 20160811 2016-05-13 2016-05-13 2.1.0
9 C End of EN Approval Procedure End of EN Approval Procedure     2016-08-11 2016-08-11
9 D Start of TB review after AP comments Start of TB review after AP comments     2016-08-11 2016-08-11
9 Dr Draft Review after PE Draft Review after PE     2016-10-11 2016-10-11 0.0.7
9 Dr Draft Review after PE Draft Review after PE     2017-01-31 2017-01-31 0.0.8
9 Dr Draft Review after PE Draft Review after PE     2017-02-01 2017-02-01 0.0.9
9 DaA Start of TB approval process Start of TB approval process     2017-02-01  
9 DaB End of TB approval process End of TB approval process     2017-03-01  
9 Da TB approval after review of AP comments TB approval after review of AP comments     2017-03-07 2017-02-22 0.0.9
9 E Draft receipt by ETSI Secretariat Draft receipt by ETSI Secretariat     2017-03-01 2017-02-22 2.1.1
10 F Start of Vote Start of Vote
Access the e-approval application
V 20170605 2017-04-06 2017-04-06 2.1.1
10 G End of Vote End of Vote     2017-06-05 2017-06-05
11 Vote result determination (adopted) Vote result determination (adopted)     2017-06-05 2017-06-05
11 WI Waiting - see "Remarks" Waiting - see "Remarks"       2017-06-05
11 Vote result determination (adopted) Vote result determination (adopted)     2019-04-05 2019-04-03
12 Publication Publication PU   2019-04-17 2019-04-09 2.1.1